May news
22nd May 2014
Been a bit quiet on the website of late, aplogies for that, so much going on.
Progress on the Geoffrey Briddon Building has slowed somewhat over the last few weeks, as we waited for quotations from potential concrete contractors for carrying out the complex floor scheme required in the shed. It also must be added that service requirements for 14 901 and the interruption brought about by Andrew's sister's wedding in May have contributed!
At the moment, the decision has been forced on us to carry out the flooring with our own labour, and “volunteers” have been sought to assist wherever possible. The next stage in the preparation work is to erect a single course of foundation blocks around the perimeter of the structure – this will act both as a tamping level for the concrete and as a base for the decorative wallstone that will form the bottom 300mm or so of the sides.
At the end of March, in compliance with the requirement laid down by the Planning Department, samples of cladding colour and wallstone were submitted for approval, having been previously told that this would take a couple of weeks. Formal approval was issued last Friday!
And as usual, back at the locos...
Teddy Bear 14 901

14 901 has continued in service normally 2 days a week and has performed without failure, although not without concerns! The temperature issues which we noticed early in April have not abated, and although taking the thermostats out and testing them showed nothing apparently untoward, the problem persisted, and at the middle of may we took the decision to remove them and blank them off for the present. Additionally, we discovered that every '14 in industrial service has received a bleed valve in the top of the cooler group, where there is a plug for the purpose, but which Swindon failed to incorporate. This has substantially reduced the time taken to fill the system to be refilled with coolant! The loco has had a service and minor changes to the fuel and lube oil arrangements that have largely stopped a leak.

With the thermostats removed, the opportunity was taken to complete the wiring of the hydrostatic fan drive system by adding another temperature switch in the top coolant pipe, and in this configuration the locomotive has been running well within temperature.

At long last we have a working speedo! Although provision for one has been available off the electronics since 2009, and provision was put into the desk, Andrew's insistence on a “traditional” 240 degree sweep has resulted in an unsuccessful hunt for a suitable display. In the end, one has been made and trialled and a second is now in manufacture.

Sentinel “Tom”
With its suspension sorted (for the present) Tom has been given a thorough workout by taking loaded steelworks trains about at Scunthorpe (picture courtesy of Toby Kirkby).

D2128
Work on a bent handrail has been proceeding, as well as stripping one buffer with a suspect spring. The ducting that is meant to prevent air recirculation within the casings has been installed. It has been agreed that the loco will NOT be available for public tours of the site until the AFRPS's diesel gala, set for the first weekend in October. So if you want a first, put the date n your diary now!
James
James has come out of hiding and is now in regular use shunting around Rowsley yard. A coolant leak has been spotted from the water pump though and must be attended to.

Ashdown
Coolant leaks have temporarily pulled this loco out of traffic, but are scheduled for early attention.
Charlie
Continues in traffic

Cheedale
When the additional compressor was fitted back at Buxton, the air filter was relocated to the opposite side even though this gave access difficulties to the equipment at the rear of the casings. It has now been put back to its original location where the mounting brackets still remained. It remains in traffic, and had a further foray to Matlock during May in connection with engineering works -top and tailing with Charlie (above).